Deliverable 1 - the 30/60/90 rollout plan
Explain the practical point behind "Give yourself 25 minutes and build the plan as if you're presenting it to the VP Eng next week."
Step 1 of 3
Give yourself 25 minutes and build the plan as if you're presenting it to the VP Eng next week. Phases, metrics per phase, the Copilot story and your top risks.
The trap in a 30/60/90 is listing activities that sound busy. A strong plan reads the other way: each phase opens with the number it moves and the activities exist only to move it. On Meridian, phase one is gated by the security review, so the first 30 days are as much about pre-empting the blocker as starting the pilot.
Learn more
Full explanation
The First 90 Days as a Pipeline
Interactive diagram. Step through it with the Next and Previous controls below, or Tab to a region to read its detail.
The security review is a gate, not a step - clear it in parallel or the whole wave stalls behind it.